Learn by Novus · Open practice pack v1
Planning and scheduling exercises: applied practice: open practice pack: learner worksheet
20 untimed questions across 4 authored sections.
This is untimed educational practice for one applied skill. It is not a clinical, diagnostic, employment, or professionally recognized assessment, it does not produce a score or credential, and for the judgement and safety families it is not a substitute for your employer's own policies, training, or legal duties.
Learner worksheet
Each item gives you a small network of tasks, a resource problem, or a plan that has met reality, and asks what follows. Choose the most defensible answer, then read the explanation. Nothing here is timed and no software is required.
Choose one answer for each item. On a judgement item, more than one option is often defensible. Pick the one you would rate most effective, then check the worked explanation for why the runner-up is weaker.
Sequencing and dependencies
Warm up on the shape of a plan: what must follow what, and what merely happens to share a resource.
1. planning-scheduling-applied-s01-q01
Task A takes 2 days and must finish before task B, which takes 3 days. Task C takes 4 days and depends on nothing. Enough people are available to run A and C at the same time. What is the shortest possible duration?
- 4 days
- 5 days
- 9 days
- 6 days
Answer:
2. planning-scheduling-applied-s01-q02
Task A must be complete before task B can begin. What is that relationship called?
- A resource constraint
- A milestone
- A finish-to-start dependency
- A lag
Answer:
3. planning-scheduling-applied-s01-q03
Two tasks are logically independent, neither needs the other's output, but both require the same single test rig.
- A resource conflict: they must be sequenced in the plan even though nothing logically requires an order
- A finish-to-start dependency between the two tasks
- A milestone clash
- Not a scheduling issue, since neither depends on the other
Answer:
4. planning-scheduling-applied-s01-q04
To recover time, two tasks that were planned in sequence are overlapped so the second starts before the first is finished. What is the principal cost of doing this?
- Materials become more expensive
- It always requires additional people
- It removes all float from the plan
- Rework risk rises, because the downstream task starts on information that is not yet final
Answer:
5. planning-scheduling-applied-s01-q05
What is a milestone in a schedule?
- A task that has no cost attached to it
- The longest task in the plan
- A point in time marking that something has been achieved; it consumes no duration itself
- A deadline imposed on the project from outside
Answer:
Resources and constraints
People are not interchangeable units of throughput. These items are about what a resource plan can and cannot promise.
6. planning-scheduling-applied-s02-q01
A task is estimated at 10 person-days. Five people are assigned to it. How long will it take?
- 2 days
- 2 days plus a small margin
- 10 days, since the total effort is unchanged
- Fewer than 10 days but usually well over 2: some parts cannot be divided, and coordination cost rises with team size
Answer:
7. planning-scheduling-applied-s02-q02
The resource sheet shows one person assigned full-time to three different tasks during the same week.
- The plan is infeasible as drawn: resolve the over-allocation by moving tasks or reassigning the work
- It is workable if they prioritise well
- It is workable provided the tasks are small
- It will resolve itself as the tasks progress
Answer:
8. planning-scheduling-applied-s02-q03
The only person qualified for a critical task is on approved leave for the two weeks in which it is scheduled.
- Assume the leave can be moved if the project needs it
- Reschedule the task, bring it forward, or arrange qualified cover, and update the committed date to match
- Start the task with someone less qualified and have it reviewed later
- Shorten the task so it fits before the leave begins
Answer:
9. planning-scheduling-applied-s02-q04
The sponsor pulls the delivery date forward by a month. The scope is fixed and the estimate was already tight.
- Ask the team to work harder for the remaining period
- Reduce the quality bar so the work goes faster
- Either cost or scope has to move; if neither does, the new date is not achievable and should be reported as such
- Extend working hours until the new date is met
Answer:
10. planning-scheduling-applied-s02-q05
Where is a project's contingency best held?
- Centrally, released against identified risks, so that it stays visible and its use is a decision
- Inside each task estimate, where the work actually happens
- At the very end of the project, after the last deliverable
- Held privately by each team lead for their own area
Answer:
Float, the critical path, and buffers
The heart of a schedule. Work out which delays matter and which do not, and where protection should sit.
11. planning-scheduling-applied-s03-q01
What is the critical path?
- The most expensive activities in the project
- The activities carrying the greatest technical risk
- The longest chain of dependent activities: any delay on it delays the whole project
- The activities the customer considers most important
Answer:
12. planning-scheduling-applied-s03-q02
A task with 3 days of float slips by 2 days. What is the effect?
- The project end date slips by 2 days
- The end date is unchanged, but only 1 day of float now remains, so the task needs watching from here
- Nothing at all changes
- This chain immediately becomes the critical path
Answer:
13. planning-scheduling-applied-s03-q03
A task that is not on the critical path slips by more than its available float.
- Nothing happens; only critical tasks affect the end date
- The float is simply recalculated with no other effect
- The critical path cannot change, by definition
- That chain becomes critical, and the project end date moves by the amount of the excess
Answer:
14. planning-scheduling-applied-s03-q04
Where should a schedule buffer be placed to protect a delivery date?
- As a single buffer at the end of the chain it protects
- Inside each task's own estimate, so each task is protected
- Before the first task, so the project starts with slack
- Spread evenly across every task in the plan
Answer:
15. planning-scheduling-applied-s03-q05
Two parallel chains both feed the same milestone. One has zero float; the other has six days.
- Give both chains equal management attention
- Concentrate on whichever chain contains more calendar days
- Concentrate on whichever chain contains more tasks
- Manage the zero-float chain as critical, while tracking the other against its six days of float
Answer:
When the plan meets reality
Finish with tracking and change. A plan earns its keep only if it is updated with what actually happened.
16. planning-scheduling-applied-s04-q01
A task on the critical path finishes three days early.
- Pull the dependent work forward if resources allow, so the gain is not silently absorbed
- Hold the plan as it was; early finishes cause confusion downstream
- Reduce the next task's estimate by three days
- Note the saving and report it at the end of the project
Answer:
17. planning-scheduling-applied-s04-q02
A task on the critical path is going to finish a week late.
- Add a week to the end date and carry on
- Ask the following teams to make the week back
- Hold the published dates and see whether it recovers
- Reforecast the affected chain and the end date, then communicate the new date together with what caused the slip
Answer:
18. planning-scheduling-applied-s04-q03
Mid-project, a stakeholder asks for an extra deliverable, describing it as small.
- Decline; the scope was agreed at the outset
- Absorb it, since it is small and refusing looks unhelpful
- Estimate it, show what it would displace or what it adds to the date, and let the sponsor choose
- Agree to it and add it after the current end date
Answer:
19. planning-scheduling-applied-s04-q04
The weekly report has shown the same task as '90% complete' for three weeks running.
- Accept it; the task is nearly finished
- Treat percent-complete as unreliable: ask what work remains, expressed in days, and what is blocking it
- Escalate immediately to the project sponsor
- Reassign the task to somebody else
Answer:
20. planning-scheduling-applied-s04-q05
The project plan is three weeks out of date because nobody has been updating it and everyone now works from memory.
- Produce a more detailed plan so that its value is obvious to everyone
- Rebuild it at a level of detail the team will actually maintain, and set a short regular update rhythm
- Accept that this project is better run without a plan
- Have one person keep it updated from their own assumptions
Answer: