Learn by Novus · Open practice pack v1

Planning and scheduling exercises: applied practice: open practice pack: answer key

20 untimed questions across 4 authored sections.

This is untimed educational practice for one applied skill. It is not a clinical, diagnostic, employment, or professionally recognized assessment, it does not produce a score or credential, and for the judgement and safety families it is not a substitute for your employer's own policies, training, or legal duties.

Answer key

ItemChoiceAnswer
planning-scheduling-applied-s01-q01B5 days
planning-scheduling-applied-s01-q02CA finish-to-start dependency
planning-scheduling-applied-s01-q03AA resource conflict: they must be sequenced in the plan even though nothing logically requires an order
planning-scheduling-applied-s01-q04DRework risk rises, because the downstream task starts on information that is not yet final
planning-scheduling-applied-s01-q05CA point in time marking that something has been achieved; it consumes no duration itself
planning-scheduling-applied-s02-q01DFewer than 10 days but usually well over 2: some parts cannot be divided, and coordination cost rises with team size
planning-scheduling-applied-s02-q02AThe plan is infeasible as drawn: resolve the over-allocation by moving tasks or reassigning the work
planning-scheduling-applied-s02-q03BReschedule the task, bring it forward, or arrange qualified cover, and update the committed date to match
planning-scheduling-applied-s02-q04CEither cost or scope has to move; if neither does, the new date is not achievable and should be reported as such
planning-scheduling-applied-s02-q05ACentrally, released against identified risks, so that it stays visible and its use is a decision
planning-scheduling-applied-s03-q01CThe longest chain of dependent activities: any delay on it delays the whole project
planning-scheduling-applied-s03-q02BThe end date is unchanged, but only 1 day of float now remains, so the task needs watching from here
planning-scheduling-applied-s03-q03DThat chain becomes critical, and the project end date moves by the amount of the excess
planning-scheduling-applied-s03-q04AAs a single buffer at the end of the chain it protects
planning-scheduling-applied-s03-q05DManage the zero-float chain as critical, while tracking the other against its six days of float
planning-scheduling-applied-s04-q01APull the dependent work forward if resources allow, so the gain is not silently absorbed
planning-scheduling-applied-s04-q02DReforecast the affected chain and the end date, then communicate the new date together with what caused the slip
planning-scheduling-applied-s04-q03CEstimate it, show what it would displace or what it adds to the date, and let the sponsor choose
planning-scheduling-applied-s04-q04BTreat percent-complete as unreliable: ask what work remains, expressed in days, and what is blocking it
planning-scheduling-applied-s04-q05BRebuild it at a level of detail the team will actually maintain, and set a short regular update rhythm